Our Technical Service team at RotoTech Bangladesh Limited recently serviced an atomizing air pre-cooler from a 330 MW dual-fuel power plant. The unit came to us with a water leakage problem on site.


First inspection
After withdrawing the tube bundle from the shell, we found heat-distorted tubes at the gas inlet end:
- 1. Tubes bent between the baffle plates (thermal buckling)
- 2. Bloating of the tube wall at the bends
- 3. Through-wall cracking of the tubes
- 4. Cracked tube-to-tubesheet welds, which opened the leak path
Leak test results
We tested the first 52 tubes with air and water under pressure. 47 of the 52 leaked, which is 90.4%. That showed the damage was general across the bundle, so plugging individual tubes would not give a reliable repair. We recommended replacing all 380 tubes.

Service procedure
- 1. Withdrew the tube bundle from the shell
- 2. PT 1: hydrostatic test of the old tubes before dismantling, to record the as-received condition
- 3. Dismantled all 380 tubes
- 4. Sourced new tubes, matching material grade, outer diameter and inner diameter to specification
- 5. Cleaned the baffle plates, tie rods and spacer tubes, and made new gaskets
- 6. Reassembled the bundle with all new tubes
- 7. PT 2: hydrostatic test of every new tube before assembly, so no defective tube was welded in
- 8. TIG (GTAW) welded each tube end to the tubesheet
- 9. PT 3: hydrostatic test of all 380 tubes and welded joints after welding
- 10. Accepted the tube assembly on zero leakage, then inserted the bundle into the shell
- 11. Fitted the new gaskets and bolts and completed the assembly









Testing at three stages means every tube and weld is proven leak-tight before the unit goes back to the plant.
Proud of the team for the careful, hands-on work on this job.